New Train for Oil Degassing & Treatment

     NEW TRAIN FOR OIL DEGASING AND TREATMENT

Client: MDOC COMPANY

Contractor: PEG Company

Subcontractor: BURJ ALSAMA CO.

Scope of Work: Mechanical Erection E&I Installation

Duration: 15-Apr-2015 and completion date 28- Feb. 2016.

 

  1. Unit 01: Crude Oil Treatment System (incl. Desalting Unit)
  2. Unit 02:Flare System(incl. KO Drums) and Closed Drain System
  3. Unit 03: Produced Water Treatment Package
  4. Unit 04: Chemical Dosing Packages
  5. Unit 05: Compressed Air Package
  6. Unit 06: Hot Oil System
  7. Unit 07: Nitrogen Production Package
  8. Unit 08: Drinking Water Production Package
  9. Unit 09: Steam Production Package
  10. Unit 10: Firefighting System 
  11. Local Technical Room (Containerised)
  12. Tie-Ins Works
Other facilities
    Regarding the PLANT, the scope of works mainly consists in the following erection works
    (but not limited to) :
  • Piping Prefabrication & Erection
  • Equipment, Machinery and Packages Erection
  • Steel Structures Erection (steel structures supplied fully prefab. and painted)
  • Fire-fighting Erection
  • Painting Erection
  • Insulation Erection
  • Electrical Installation
  • Instrument and Control Systems Installation
  • Pre-commissioning
  • Commissioning 
  • Finishing works and Punch list execution
  • As-Built Drawings implementation