Instrumentation works for Erbil Refinery- the second expansion project.

The Installation & calibration of instrumentation for Erbil refinery – second expansion project (capacity of 20 000 barrels / day) and Enhancing Gasoline Unit (capacity of 8000 barrels / day).

Duration: April 2010 - August 2010.

Our works summarized in the following points:

  • Installation of more than 1000 instrument equipments.
  • Manufactured and installed the supports of cable Tray.
  • Installed of cable tray for more than 2600 meters length.
  • Cables installation for more than 26000 meters length.
  • Instrument boards installation (38 Boards).
  • Installation of all instrument junction boxes.
  • Cables termination.
  • Continuity test.
  • Issued of Instrument Mechanical Completion Certificate ( IMCC ).